Highway 64/69 closure extended to May 24

Image
Body

By Becky Long

Publisher

 

The temporary closing of NC 69 and US 64 to Fort Hembree Road has been extended through May 24, according to a memo sent Monday from N.C. Department of Transportation Resident Engineer Adam Dockery.

The 11 day extension is due to wet weather and other unforeseen issues

Dockery said unexpected existing conditions have posed constructibility issues and the closure is necessary to excavate, grade, install drainage and pave the new alignment.

Last week the Progress asked Dockery why construction could not be done at night when there is less traffic and those road conditions were part of the reason why they can’t.

“Because of the grade change between the existing and new, it’s not safe for the traveling public to have access to this section of road during the day,” Dockery explained.

He said the existing road will be lowered approximately 4 feet, therefore and the road must stay closed until the work in complete.

There is a detour route in place  that begins at the intersection of US 64 and Business 64 and ends at the intersection of Business 64 and NC 69 (at the roundabout).

While the temporary road closing is expected to last a few more weeks, completion of the entire road project along 69 has been moved from July to September 2024.

Again Dockery offered apologies on behalf of the DOT for inconveniences the road closure may have created. He also emphasized the importance of safety.

“All are encouraged to drive with caution and obey the posted speed limits.” he said.

Dockery can be contacted by phone at (828) 321-5061.